Madagascar - Time required to build a warehouse

Time required to build a warehouse (days)

Time required to build a warehouse (days) in Madagascar was 194.00 as of 2019. Its highest value over the past 14 years was 194.00 in 2019, while its lowest value was 143.00 in 2005.

Definition: Time required to build a warehouse is the number of calendar days needed to complete the required procedures for building a warehouse. If a procedure can be speeded up at additional cost, the fastest procedure, independent of cost, is chosen.

Source: World Bank, Doing Business project (http://www.doingbusiness.org/).

See also:

Year Value
2005 143.00
2006 143.00
2007 143.00
2008 174.00
2009 174.00
2010 174.00
2011 174.00
2012 174.00
2013 176.00
2014 194.00
2015 194.00
2016 194.00
2017 194.00
2018 194.00
2019 194.00

Classification

Topic: Private Sector & Trade Indicators

Sub-Topic: Business environment